Donate now
A completed Shannon class lifeboat inside the All-weather Lifeboat Centre’s spray booth

How to build a Shannon class lifeboat

Photo: RNLI/Nigel Millard

The Shannon class lifeboat can reach 25 knots and handle hurricanes. But how is it made? We’re taking you behind the scenes to find out.

Welcome to the RNLI All-weather Lifeboat Centre. This factory in Poole, Dorset, is where we build our Shannon class lifeboats and maintain the other all-weather lifeboats in our fleet. Teams of engineers and boatbuilders work tirelessly to ensure our all-weather lifeboats are ready to launch into the roughest conditions to save lives at sea. 

Here’s Daniel Sharp, Production Control Manager at the All-weather Lifeboat Centre, to tell us about the 17-month journey that begins on a factory floor and ends with launching a lifesaving legend.

Daniel Sharp, RNLI Production Control Manager, in front of a Shannon class lifeboat

Photo: RNLI/Nathan Williams

Daniel Sharp, Production Control Manager at the All-weather Lifeboat Centre

Step one: Composite build 1

Duration: 12 weeks

‘In the first build stage, we create the Shannon class’s hull and wheelhouse,’ says Daniel. ‘We do this using SPRINT™ composite material – that’s glass and carbon fibre, with a layer of epoxy resin on one side. The composite material is laid into empty moulds and cooked overnight under vacuum pressure. This creates the structure of the hull and wheelhouse.’

With the outer shell created, the boatbuilders then add bulkheads (upright walls which divide the boat into six watertight compartments) and stiffeners (longitudinal beams which give the hull extra rigidity to withstand slamming in rough seas). These are glued and bonded into place.

Then the hull and wheelhouse are lifted out of the moulds and moved to the next stage.

A Shannon class lifeboat’s hull is being constructed in the All-weather Lifeboat Centre. The hull is made of bright green composite material.

Photo: RNLI/Nathan Williams

The Shannon’s hull is constructed from composite material, laid into moulds and cooked overnight under vacuum pressure 

Step two: Composite build 2

Duration: 12 weeks

With the structures of the hull and wheelhouse complete, the next step is to install the lifeboat’s composite furniture. ‘That’s things like fan casings, stowages (like cupboards), and vent boxes in the engine room,’ explains Daniel.

At this stage, the hull and the wheelhouse are still separate, but the team temporarily put the hull and deck joints together to make sure they’ll be a perfect fit – this is called dry fitting. ‘We use non-stick tape for this, so the resin doesn’t stick,’ says Daniel. ‘If we joined the hull and wheelhouse together permanently at this stage, it would be hard to get people in and out for the rest of the build.’

Next, around 1,500 fibreglass pads and fixings are accurately positioned and glued onto the surfaces of the structure so that more components, like the two 650hp Scania engines, pipework and electrical boxes, can be fitted once the boat is painted. ‘The pads and fixings mean we can assemble everything like flatpack furniture after painting,’ says Daniel. ‘No drilling holes, no gluing.’

There’s more to fit during this stage too, such as the twin Hamilton waterjets, each with a movable nozzle to provide steering and a bucket assembly to give the boat reverse thrust. The Shannon is our only all-weather lifeboat to be powered by waterjets rather than traditional propellers. Waterjets allow the lifeboat to operate in shallow waters and to be intentionally beached if needed, and they make the boat more agile and manoeuvrable.

Boatbuilders will also fit the main keel shoe (a 10mm thick section of metal that goes on the hull for protection), side keels (fin-like additions which help to stabilise the boat) and spray rails (which are added to the side of the hull to redirect sea spray).

The hull of the Shannon, divided into sections. The hull is a muted green colour, and a man is fitting it with small pads and fixings, which will be used to install composite furniture.

Photo: RNLI/Nathan Williams

The hull of the Shannon, fitted with pads and fixings

Step three: Painting

Duration: 7 weeks

During this stage, the hull and wheelhouse are painted inside and out. The wheelhouse interior is painted matte black to reduce reflections at night and the hull bottom is painted with an abrasion-resistant ice-breaker paint to prevent hull wear during beach recoveries, with antifoul over the top. Daniel explains: ‘Antifoul is a special type of paint that prevents marine organisms from growing on the hull. You’ll quickly see a lot of seaweed and barnacles otherwise! The paint is self-eroding, so when the marine organisms try to bond to it, it sheds.’

A freshly painted Shannon class lifeboat, in a white spray booth

Photo: RNLI/Nathan Williams

A Shannon class lifeboat is painted inside the All-weather Lifeboat Centre’s spray booth

Step four: Fit out 1

Duration: 12 weeks

Next, the components mentioned in step two are fitted to the hull and wheelhouse, using the fibreglass pads and fittings. ‘The aim is to complete as much of the fit out as possible while the hull and wheelhouse are still separate,’ Daniel says.

All the hull cables are installed and made ready to be fitted. A collapsible mast is also fitted to the wheelhouse, and capstans and bollards are fitted on the deck. ‘A bollard is a metal pole with two horns stuck on to secure ropes for towing,’ says Daniel. ‘A capstan is similar but motorised – it has a winch on top that spins around to pull the ropes in.’

A woman is installing multi-coloured hull cables to the Shannon class lifeboat in the All-weather Lifeboat Centre

Photo: RNLI/Nathan Williams

Installing the hull cables

Step five: Fit out 2

Duration: 12 weeks

This is the final build stage before the lifeboat is trialled. First, the wheelhouse is glued to the hull to create the hull-to-deck joint. The deck then has fendering (big rubber bumpers), stanchions (vertical poles which hold up the guardwires on the perimeter of the boat to stop people falling overboard) and cleats (deck hardware you tie ropes to) fitted. We install windows and add decals (the large letters/numbers on the boat).

The wheelhouse electronic cables are also fitted, with cables going in and coming up from the hull. ‘The hull and wheelhouse are connected as a system, so it all works as one boat,’ says Daniel.

Finally, the seats are installed – and the boat is powered on. ‘We then start commissioning, which means testing the systems are all working,’ says Daniel. ‘Then it’s out of the factory, and on to trials.’

Two lifeboats are being fitted out in the All-weather Lifeboat Centre

Photo: RNLI/Nathan Williams

The final build stages for the Shannon class lifeboat 

Step six: Launch and trials 

Duration: 7 weeks

The Shannon is moved from the lifeboat factory. ‘Then it’s launched with a small ceremony to celebrate it getting wet for the first time, ahead of 50 years of service,’ says Daniel. The two Scania Power Solutions engines are fired up.

Then the lifeboat begins its harbour acceptance trials and sea trials. ‘We call these HATs and SATs,’ says Daniel. ‘The harbour acceptance trials take place with the Shannon sitting alongside in the harbour – the boat doesn’t go anywhere. You don’t want to go out to sea and realise you lifeboat can’t steer.’ These trials include an inclining experiment to check the stability of the boat and to ensure the boat could self-right if needed, and a hose test to check for leaks.

Next, the Shannon moves out from the harbour and onto its sea trials. ‘In week 5 of this 7-week process, the Operations Proving Team take the boat for a week to test it thoroughly and ensure the boat is operating correctly,’ says Daniel. ‘Once this is complete, the boat is officially accepted and signed into the fleet.’

A navy blue and orange lifeboat is winched into the water at the All-weather Lifeboat Centre

Photo: RNLI/Nathan Williams

A newly built Shannon class lifeboat is lowered into the water for the first time

What happens next?

Now it’s time for the crew to collect their boat. They usually stay at the RNLI College in Poole for training and to get to know their new Shannon class lifeboat. They might sail the boat back to their station as part of their training too. ‘If the station is very far away, the lifeboat might be driven by road halfway and then sailed the rest of the way home,’ says Daniel.

The crew – and their Shannon – arrive to an emotional welcome from volunteers and the local community. They’ll continue their training at the station to make sure everyone is competent on the boat. Once the training is complete, the boat will be declared on service and the naming ceremony will take place. This is a proud day of celebration, with songs and speeches, and marks a new chapter for lifesaving at the station.

A completed model Shannon class lifeboat in front of a real RNLI Shannon class lifeboat

Photo: RNLI/Lee Hawkins

Just like the real thing!

Fancy trying your hand at boatbuilding? You can paint and assemble your own Shannon class lifeboat with an Airfix model kit.

Buy yours at the RNLI Shop.

Build your own Shannon

Categories